BUILDING FOR LEARNING 

Tentative Timeline for 2016 Bond Projects

 
Olympic Timeline Date New Elementary Bond Timeline Date Dick Scobee Timeline Date Pioneer Timeline Date Lea Hill Timeline Date  New Elementary Bond Timeline Date Chinook Timeline Date
Terminal Park Timeline Date
 
  
In November 2016, the Auburn community passed a $456,056,000 bond to replace six aging schools and build two new elementary schools.

 
The bond will replace:
Chinook Elementary, built in 1963
Dick Scobee Elementary, built in 1954
Lea Hill Elementary, built in 1965
Olympic Middle School, built in 1957
Pioneer Elementary, built in 1959
Terminal Park Elementary, built in 1945
 
The two new elementary schools will provide increased classroom space.
 
Thanks to the tremendous support of the community, the Auburn School District is going to build eight amazing schools that will serve the community for generations.
 
The timeline for completing all of the projects is eight to 10 years. Olympic will be the first school and work is already underway.  The current project timeline is tentative.  The district continues look for property for the new elementary schools and, once the sites are finalized, the timeline will be updated.
 
Questions may be directed to building4learning@auburn.wednet.edu.


To follow the progress for each school, click on the school name below:
  • Olympic Middle School

    Timeline: Planned Opening, September 2019

    Plan: Olympic will be rebuilt on the existing site while the current school building remains in operation. The new school will be built on the south side of the property. The existing building will be used as an interim school for some or all of the five elementary schools as they are replaced. Construction begins in the spring of 2018.

    Comments (-1)
  • New Elementary School Bond Timeline Information

    New Elementary

    Tentative Timeline: 2020

    Plan: The district is actively searching for property to build the two new elementary schools. One school will be in the north end of Auburn and one will be in the south. Once property is acquired, a more definitive timeline will be developed for the construction of the new elementary schools.

    Comments (-1)
  • Dick Scobee Elementary

    Tentative Timeline: 2020

    Plan: Dick Scobee will be rebuilt on the existing site. Students will attend Olympic as an interim facility for one year while the existing school is razed and rebuilt.

    Comments (-1)
  •  New Elementary Bond Timeline Information

    New Elementary

    Tentative Timeline: 2021

    Plan: The district is actively searching for property to build the two new elementary schools. One school will be in the north end of Auburn and one will be in the south. Once property is acquired, a more definitive timeline will be developed for the construction of the new elementary schools.

    Comments (-1)
  • Lea Hill Elementary

    Tentative Timeline: 2021

    Plan: Lea Hill will be rebuilt on the existing site. Students will attend an interim facility for one year while the existing school is razed and rebuilt. The interim site has not been determined, but using the old Olympic Middle School is one possibility.

    Comments (-1)
  • Pioneer Elementary

    Tentative Timeline: 2021

    Plan: Pioneer will be rebuilt on the existing site. Students will attend Olympic as an interim facility for one year while the existing school is razed and rebuilt.

    Comments (-1)
  • Chinook Elementary

    Tentative Timeline: 2022

    Plan: Chinook will be rebuilt on the existing site. Students will attend Olympic as an interim facility for one year while the existing school is razed and rebuilt.

    Comments (-1)
  • Terminal Park Elementary

    Tentative Timeline: 2023

    Plan: Terminal Park will be rebuilt on the existing site. Students will attend Olympic as an interim facility for one year while the existing school is razed and rebuilt.

    Comments (-1)